Progress of this case since the Judgment of DKD CDR Forum on 15-10-2009After the judgment dated 15-10-2009 at DK-DCD-R Forum Mangalore, builder started dismantling the unfinished GF office with one or two labourers. Other works mentioned in the judgment was not even started / done till date. For DOD, he has not produced all the necessary documents to the lawyer. We were keeping a watch on the website http://kscdrc.kar.nic.in/ . Our builder has appealed in the higher court at KSCDR Commission Bangalore against the judgment we got this news on 16-11-2009. At KS CDR Commision gave its judgment on 23 September 2010. Builder's appeal is dismissed. This DKDCDRF judgment has been confirmed by the KS-CDR Commission at Bangalore as "JUST and PROPER" Builder's appeal at National Consumer Disputes Redressal Commission has been dismissed at the admission stage and confirmed that "the compensation granted is proper and flat owners have been harassed for over number of years." Hence builder should accept the judgment gracefully or he must face the consequences for not adhering to the judgment. Builder never approached us for any concession before this date. Arrest warrant was issued by DKDCDRF. Builder surrenders on the last day at DKDCDRF. Builder promises to work out compromises. He never contacted us with clean proposal. He was trying to push for us to agree to include PENT HOUSE and 4 extra car parks in the DoD. We are not ready to accept any illegal thing in our building for the DoD. Personal data of the flat buyers in the draft submitted by builders lawyer was not accurate. Compiling the flat owners details accurately is the responsibility of the Builder. Hence there was no progress on drafting of DoD. Builder started external painting, completed half of the work and stopped without painting on the eastern and southern side of the building. During the ADALAT session on 23-02-2011, Hon. Judge asked the builder to complete the work as stated in the DKDCDRF judgment. Builder wanted two more months to complete the work. Hon. Judge asked to report progress after one month 23-03-2011. See the ADALAT report of 23-02-2011 DKD CDRForum - ADALAT SESSION on 23rd February 2011.Present from our side: Mr.Anand Rao, Mr.Prabodh C. Bolur, Mr.Rajesh Shenoy, Mr.Manish Dugar, Mr.Thalithaya, Ms Manjula advt. Present from OP: Mr.Ganesh Shetty, (Builder) Mr.Dayanand Rai Advt. Preamble: DKD-CDR Forum's judgment dated 15-10-2009 confirmed wrong-doings of the builder. This judgment has been confirmed by the KS-CDRCommission at Bangalore as "JUST and PROPER" and builder's appeal at National Commission has been dismissed at the admission stage and confirmed that "the compensation granted is proper and flat owners have been harassed for over number of years." Hence builder should accept the judgment gracefully or he must face the consequences for not adhering to the judgment. Builder never approached us for any concession before this date. Issues discussed with Hon. Judge Smt. Asha Shetty & two other Forum Members at DKDCDRForum.
|